This document fixes the target environment for fi-fhir 1.0 evidence. It is a test contract, not a claim that the current pre-1.0 repository has completed every release, conformance, performance, recovery, or compatibility gate.
Status vocabulary
- locked: the repository and required CI already enforce this choice;
- reference target: future 1.0 proof must use this exact profile unless a dated architecture decision changes it;
- release gate: still requires archived end-to-end evidence before 1.0.
Platform matrix
| Area | 1.0 baseline | Current status |
|---|---|---|
| Security domain | One logical healthcare-organization security domain per deployment; tenant and actor identity remain mandatory on runtime and durable contracts | Reference target; shared multi-tenant hosting is not a 1.0 claim |
| Backend toolchain | Go 1.26.5 | Locked by go.mod, CI, and the production image build |
| UI and SDK toolchain | Node.js 22 and npm 10.9.3 | Locked by CI and frozen npm lockfiles |
| Runtime OS/architecture | Linux amd64 reference; Linux arm64 release target | amd64 is the reference target; arm64 needs release-gate runtime evidence |
| Persistence | PostgreSQL 16 | Locked for Compose and CI integration services; production recovery evidence remains a release gate |
| Local deployment | Docker Compose with PostgreSQL 16 | Development reference; not a production topology |
| Kubernetes deployment | Kubernetes 1.36.x through Helm and Kustomize | Pinned reference target; render, install, upgrade, rollback, and live golden-journey evidence remain release gates |
| Authoring UI | Current SvelteKit build served as static assets | Build/test locked; latest-two Chrome, Edge, and Firefox plus current Safari compatibility remains a release gate |
| Healthcare standards | FHIR R4 4.0.1, US Core 9.0.0, SMART App Launch 2.2.0, Bulk Data 3.0.0 | Release targets. For FHIR R4 / US Core, the HL7 official validator (validator_cli.jar 6.10.4) runs offline in CI as a blocking gate (Slice 5.1c-β) over the mapper's fixtures and the Bundles the fhir transport delivers, against 23 pinned packages with no terminology server, and its findings — errors included — are held to an exact-equality ledger: official-validator evidence exists, a clean pass and a certificate do not (docs/planning/FHIR-CONFORMANCE-MATRIX.md §5.2). SMART App Launch 2.2.0 and Bulk Data 3.0.0 have no validator or conformance-suite evidence yet. Since Slice 5.1b the repository pins hl7.fhir.r4.core#4.0.1 and hl7.fhir.us.core#9.0.0 as offline .tgz under testdata/fhir/packages/ and resolves against them — see "FHIR profile-version assertion policy" below for exactly what that does and does not establish. Since Slice 4.1c-c the durable engine delivers Patient/Encounter (ADT) and DiagnosticReport/Observation (lab) over the fhir transport as conditional transaction Bundles. |
Kubernetes 1.36 is the pinned minor because it is an actively supported upstream release during the Engine Alpha program. Patch releases may advance within 1.36 for security and defect fixes; changing the minor requires a dated decision and a full deployment proof rerun.
FHIR profile-version assertion policy
Decided 2026-08-09, Slice 5.1a. Recorded in .loom/40-decisions.md and
docs/planning/FHIR-CONFORMANCE-MATRIX.md; asserted by
TestFHIRConformance_ProfileVersionPolicy.
The mapper asserts bare canonicals. The checker accepts a bare canonical or any
|version-pinned form of it.
Concretely, a resource this product emits declares
http://hl7.org/fhir/us/core/StructureDefinition/us-core-patient, never
…/us-core-patient|9.0.0. A resource this product validates may declare either.
Two consequences worth stating plainly, because the row above lists US Core 9.0.0 and a reader could reasonably infer more than is true:
- The mapper's own output is not version-pinned, and the packages now are.
None of the 32 US Core profile constants carries a version suffix, and that
stays deliberate. What changed in Slice 5.1b is that
hl7.fhir.r4.core#4.0.1andhl7.fhir.us.core#9.0.0are checked in as offline.tgzundertestdata/fhir/packages/with sha256 sums verified on every test run, and a resolver reads them. Both archives reproduce the registry-publisheddist.shasum. All 32 constants resolve to a real US Core 9.0.0 profile. 9.0.0 is still a release target for the product's behaviour; it is now a fact about what the repository validates against. - The shipped checker is still a required-element and profile-URL presence
check, not a profile validator.
pkg/fhir/validate.gois unchanged by 5.1b. It has no terminology bindings, no primitive-type checks, no slicing, and no invariants. - The new structural validator resolves, and still is not the official
validator.
pkg/fhir/structural.go(Slice 5.1b, Option C) checks, against the pinned archives: resource type existence in R4 4.0.1; profile resolution, resource-type agreement andbaseDefinitionchain termination; and cardinality —min,max, prohibition — from the R4 base snapshot and every resolved profile snapshot, at every element depth. It reports unpopulated must-support elements without failing on them, because US CoremustSupportbinds the system rather than the instance. It does not evaluate terminology bindings, FHIRPath invariants, slicing, primitive-type formats, reference targets, or extensions, and it issues no conformance certificate. - The official validator now runs too, and is still not a pass.
validator_cli.jar6.10.4 (Option A, Slice 5.1c-β) validates the mapper fixtures and the delivered Bundles offline in CI — invariants, slicing, datatype rules and local code-system membership included, external terminology not — and holds every finding to an exact-equality ledger that still records errors. It does not close item 7 of the evidence list below: the FHIR ledger still records errors, and SMART App Launch and Bulk Data have no evidence at all.
The alternative — pinning all constants to |9.0.0 and requiring an exact match —
was rejected in 5.1a. Without a package-resolution step a pinned constant asserts
a version it cannot verify, and it would reject a correct bare canonical. The
package-resolution step now exists, so the tolerance has teeth it did not have:
…/us-core-patient|9.0.0 resolves against the pinned package and
…/us-core-patient|8.0.0 is rejected, where 5.1a's suffix-stripping accepted
both. Re-pinning the constants is still not planned — a bare canonical is what a
US Core publisher is expected to emit — but the reason has narrowed from "we
cannot verify a version" to "we choose not to assert one".
Running the structural validator over the mapper's own generated fixtures now
finds nothing: all twenty-five files are clean and the structural ledger is
empty as of Slice 5.1c-α (2026-09-24), which closed the seven cardinality
violations Slice 5.1b measured — including the DocumentReference content gap
that violated base R4 as well as US Core. The empty ledger is still held to
exact equality by make fhir-structural, so a violation that reappears fails
the build, and the official validator independently reports no cardinality
finding on the same fixtures. That is cardinality only: the official
validator's ledger still records errors of other kinds
(docs/planning/FHIR-CONFORMANCE-MATRIX.md §5.2). A reader sizing up this row
should read §5.1 and §5.2 before quoting the standards row.
Reference application profile
The performance and recovery gates use this application-side reference profile:
- Linux amd64;
- 4 vCPU and 8 GiB RAM per application replica — not across the
deployment. Kubernetes
resourcesare per container, so a total figure cannot be expressed in the values file that carries the profile, and halving the envelope to make the prose match would be a capacity change made on no measurement. Two replicas therefore total 8 vCPU / 16 GiB; - two application replicas for Kubernetes scenarios;
- PostgreSQL 16 on SSD-backed persistent storage;
- destinations decoupled from durable acceptance for latency measurements;
- 2-KiB HL7v2 messages for the baseline throughput journey.
The chart defaults are not the reference profile
deploy/helm/fi-fhir/values.yaml requests 100m CPU and 128Mi memory and
limits each pod to 500m CPU and 512Mi memory. A 4 vCPU / 8 GiB budget
cannot be met inside a 500m limit, so the chart defaults and the profile
above are not two views of one thing — they are a scheduling default and a
measurement target that happen to live in the same repository.
Slice 4.4a resolves the contradiction by naming it rather than by moving a number. Raising the chart defaults to the profile would change what every existing deployment schedules, on the strength of a profile nothing has yet measured against — a capacity claim dressed as a chart edit.
The resolution:
- The chart defaults stay. They are what a small or evaluation deployment
should schedule, and they are labelled as scheduling defaults in
values.yamlitself. deploy/helm/fi-fhir/values-reference-profile.yamlcarries the profile. It sets requests and limits to the 4 vCPU / 8 GiB envelope and two replicas, and is the file any performance run must use:helm install ... -f deploy/helm/fi-fhir/values-reference-profile.yaml.- Slice 4.4b built the harness and made the runner decision (see the
budget table below). The decision was not "wait": CI's k3s pool spans hardware
differing by more than 5×, so a latency budget measured there is either
permanently red or calibrated into meaninglessness — but allocation counts do
not depend on the machine, so the durable accept path is now gated on those,
blocking, in the ordinary pool. Wall-clock and throughput are measured by a
job restricted to the pinned
fi-fhir-perfrunner identified in Sprint 6 planning. Its presence is not certification evidence.
Until an accepted run archives the required measurements, no document may describe the chart defaults, or the reference profile, as proven capacity. The profile is the environment a future measurement must use; it is not a claim that the software performs at that scale.
Required evidence before a 1.0 support claim
The following remain blocking:
- Golden Path 001 production/preview parity, durable receipt, duplicate, restart, and profile-revision tests;
- authenticated HTTP and MLLP protocol journeys;
- Helm and Kustomize render plus Kubernetes 1.36 install, upgrade, rollback,
and uninstall proof — render and schema validation closed by slice 4.4c
(
scripts/validate-k8s-schema.sh, blocking inlint:helm): the chart at default values, the chart at the reference profile, the Kustomize base, and the production overlay all validate-strictagainst the pinned 1.36 API schemas, with a negative control that must be rejected. Both application Deployments now declare a rolling-update budget, a grace period, and apreStop, and the PostgreSQL Deployment usesRecreateso it cannot wedge on its ReadWriteOnce volume. Live install, upgrade, rollback, and uninstall evidence on a 1.36 cluster remains blocking and is the last RC item; - PostgreSQL backup/restore and the documented RTO proof — closed by slice
4.4c:
test:migration-compatibilityproves the restore is faithful (rows, PHI payloads, immutability guards attributable to those guards by SQLSTATE, theNOT VALIDprovenance CHECK, and every schema ledger at its declared version — six at certification, seven since the connection catalog), proves the delivery worker resumes from the restored state, and archives a measured recovery time asrecovery-rto.json. The RPO half stays open and is an operator responsibility with a stated method, not a product claim: bounding data loss to minutes requires continuous WAL archiving and point-in-time recovery, which belongs to whoever runs the database. Seedocs/operations/PRODUCTION-HARDENING.md, "What this repository claims, and what it hands to the operator", and.loom/40-decisions.md(2026-08-09, "WAL/PITR posture"); - reference-profile latency, throughput, soak, and recovery reports (budget by budget, below);
- browser/accessibility matrix evidence;
- official healthcare standards conformance evidence where applicable;
- security, PHI, secret, tenant-isolation, and audit kill-tests.
Performance and recovery budgets, one by one
The word "harnessed" below is doing real work. It means the path is measured and a regression in it fails a blocking CI job — and it does not mean the numeric budget has been demonstrated. Those are different claims and this table keeps them apart on purpose.
| # | Budget | Status | What exists, and what is missing |
|---|---|---|---|
| 1 | Authenticated MLLP and HTTP durable-accept latency (p95 ≤ 250 ms, p99 ≤ 500 ms) | Certified on the serial accept paths — runner 8, 2026-09-25 | Three plays of test:performance-profile on identical main code (4d8f31a8c, pipeline 28955; jobs 308841, 309005, 309029) on runner 8 (fi-fhir-perf, Intel(R) Xeon(R) CPU E5-2680 v4 @ 2.40GHz, 4 CPU / 8 GiB, PostgreSQL 16 in the pod, one replica) each archived a performance-report.json with certified: true: serial IngressSubmit p95 9.4–9.9 ms / p99 11.4–13.3 ms, serial MLLPSubmit p95 9.4–10.0 ms / p99 10.3–11.4 ms, and the RunParallel variants p95 38.9–50.6 ms / p99 53.5–65.2 ms — every figure at least four times inside the target. The harness is proven sensitive: job 308698 on the same runner with -tags perfregress (a 300 ms sleep per accept) reported certified: false, failed_budget: 1, p95 ≈ 311 ms. Host stability: the serial paths spread ≤ 1.06× across the three runs and MLLP-parallel 1.11×, inside the ≤ 1.15× rule; HTTP-parallel spread 1.24×, so the parallel figures are reported, not certified — RunParallel contention on four CPUs beside the database is scheduler-dependent (the Slice 4.4b finding), while the serial paths show the host itself is stable. Scope: the in-process durable-accept path — ingress and MLLP Submit against PostgreSQL — excluding the HTTP handler, bearer/HMAC validation, TLS, and MLLP framing. Ordinary CI still gates only allocs/op. |
| 2 | One-hour steady-state throughput on the reference profile | Harnessed, uncertified | Slice 4.4e's per-deployment MLLP rate quota has merged, and the profile job now reports this budget as harnessed with its gap stated in the report: it runs 300 accepts per benchmark in one process, while the budget is the declared 250 two-KiB messages per second sustained for one hour against two replicas of the reference profile. A one-hour variant of the single-process harness was considered and rejected on 2026-09-25 (decision entry): it would certify a different claim. |
| 3 | 1-GiB batch import peak memory above idle | Not measured — sampler only | "Harnessed" overstated this row until 2026-09-25: no workload in internal/integration/perf imports a batch, and perf.HeapSampler runs only in a 32 MiB unit test and reads HeapAlloc, not the cgroup RSS the budget is written in (a Go process's RSS includes heap the collector has freed and not returned to the OS, so RSS is a property of GC timing as much as of the workload). The profile job now reports it as not_measured. Certification needs its own slice: a 1-GiB batch-import workload on runner 8 reading peak RSS from the cgroup and proving restart from the last durable checkpoint. |
| 4 | Recovery time objective | Not started — slice 4.4c | 4.4a proved a pg_dump/restore round-trip preserves every durable row and trigger. It measured no recovery time. |
| 5 | Recovery point objective | Known unachievable as configured — slice 4.4c | PRODUCTION-HARDENING.md states it directly: logical dumps cannot meet a minutes-scale RPO, and nothing in this repository configures WAL archiving or PITR. |
| 6 | One-version rollback safety | Certified — slice 4.4a | N-1 defined per migration ledger, a real defect found and fixed (0004_export_attribution.sql made three columns NOT NULL with no DEFAULT, so rollback failed every session export), and a restore round-trip proof in CI. |
| 7 | Golden-journey evidence on Kubernetes 1.36 | Not started — slice 4.4c | Needs a cluster. |
In ordinary CI, budgets 1, 2 and 3 are gated on allocations only, and that gate is narrower than it sounds — budget 1's wall-clock is asserted only by the pinned-runner profile job cited in row 1. Measured over three runs, the durable accept path's allocation count varies by about 2 in 4650 — stable, but not the bit-identical figure the legacy micro-benchmarks report. A ceiling roughly 1% above the observed count detects a regression of some 40 allocations per message. It will not notice one. It is a regression detector for the thing that causes latency, not a measurement of latency.
How budget 1 was certified, and what remains. FI_FHIR_PERF_RUNNER=1 was
set on 2026-09-24. Runner 8's job pod — fixed at 4 CPU / 8 GiB plus its helper
and PostgreSQL service, 11 GiB of requests in all — could not schedule beside
the node's resident inference server until the operator lowered that server
pod's memory request in place for the run window (Kubernetes 1.33 pod
resize; the model was neither restarted nor scaled). The negative control ran
first, then three plays on identical code; the four performance-report.json
artifacts are the evidence cited in row 1, and a green ordinary MR pipeline
still supplies none of it. Budget 2 needs a one-hour two-replica run and
budget 3 needs a workload that does not exist yet; the profile job supplies
neither, and both stay open.
Until those gates pass, documentation must describe individual capabilities and their evidence rather than label the whole product “1.0 certified,” “HIPAA compliant,” or standards conformant.